Step 1: A Post Hole Is an Excavation
Digging a post hole feels small, but the California rules treat it as excavation. 8 CCR §1540(b) defines an excavation as "any man-made cut, cavity, trench, or depression in an earth surface, formed by earth removal." The License Law and Reference Book (Section IV, Chapter 4, p. 62) says the notification duty applies to "any person or entity who plans to disturb the surface of the ground by digging, drilling, boring, etc." An auger hole for a fence post qualifies, so the 811 call comes before the first hole, not after a line is hit.
Step 2: The Call and the Timing Window
Contact the regional notification center, 811 or (800) 640-5137 (the call is free), at least two working days but not more than 14 calendar days before work starts, except in an emergency (License Law Book p. 62; 8 CCR §1541(b)(2) also requires at least 2 working days). The center issues an inquiry identification (ticket) number, and the book notes that an excavation permit is not valid without it (p. 61). Every contractor or subcontractor excavating at the jobsite must have its own ticket number, so the fence contractor cannot rely on the grading contractor's ticket (p. 62).
The remaining 4 steps, the worked example and the quiz are in the course. This is a preview. The full lesson, with the step-by-step explanations, a worked example and a quick-check quiz, is inside the classroom.
Independent exam preparation. Contractors Classroom is not affiliated with the Contractors State License Board, and no course can guarantee a passing result.