  1. Minimum Thickness and Strength
  2. Site Preparation and Base Course
  3. The Vapor Retarder and Where It Is Not Required
  4. The Capillary Break
  5. Keep the Steel Up Where It Works

The worked example in the course applies this lesson to a realistic job in 5 steps, from "Check thickness" through "Vapor retarder for the heated room".

What you'll be able to do

  • Explain the main idea of "Slab-on-Ground: Thickness, Base, Vapor Retarder and Capillary Break" in plain language you can use on the exam.
  • Apply this step with confidence: "The Vapor Retarder and Where It Is Not Required".
  • Apply this step with confidence: "The Capillary Break".
  • Apply this step with confidence: "Keep the Steel Up Where It Works".
  • Test yourself on the worked example and the quick-check quiz inside the classroom.
SLAB-ON-GROUND REQUIREMENTS2025 CBC 1907, 2025 CRC R506 and 2025 CALGreen 4.505.2SLAB-ON-GROUND SECTIONslab 3-1/2 in min6-mil poly,laps 6 in min4-in base,1/2-in clean agg.undisturbed soilCALGreen 4.505.2.1: retarder in direct contact withthe slab, on a 4-in base of 1/2-in or larger clean aggregateVAPOR RETARDER REQUIRED?Heated room additionYESDetached unheated garageNODriveway, walk, patioNOUnheated storage under 70 sq ftNORoom slab 28 x 36 ft = 1,008 sq ftConcrete at 4 in: 1,008 x 4 / 12 = 336 cu ft336 / 27 = 12.44 cu ydAt the 3-1/2 in minimum: 10.89 cu yd4-in base: 336 cu ft = 12.44 cu ydExceptions: CBC 1907.4, CRC R506.3.3Heated room: 6-mil retarder lapped 6 in over a 4-in aggregate base12.44 cu yd of concrete and 12.44 cu yd of base for the 4-in slabDetached unheated garage slab: no vapor retarder required (CBC 1907.4 exception 1)Source: 2025 CBC 1907.3, 1907.4; 2025 CRC R506.1, R506.3; 2025 CALGreen 4.505.2.1CC
The diagram for this lesson, exactly as it appears in the Learning Hub.

The first steps of this lesson

Step 1: Minimum Thickness and Strength

A concrete floor slab supported directly on the ground must be not less than 3-1/2 inches thick (2025 CBC 1907.3; 2025 CRC R506.1, which sends expansive soils to R403.1.8). R506.1 says the specified compressive strength comes from Table R402.2. CBC 1907.1 and 1907.2 split slabs into structural slabs-on-ground, which carry vertical or lateral loads from the structure to the soil or foundations, and nonstructural slabs, which still must meet 1904.2, 1907.3 and 1907.4.

Step 2: Site Preparation and Base Course

Under R506.3, everything inside the foundation walls has vegetation, topsoil and foreign material removed. R506.3.1: fill must be free of vegetation and foreign material and compacted for uniform support, and unless approved the fill depth may not exceed 24 inches for clean sand or gravel or 8 inches for earth. R506.3.2: where the slab is below grade, place a 4-inch-thick base course of clean graded sand, gravel, crushed stone, crushed concrete or crushed blast-furnace slag passing a 2-inch sieve; no base is needed on well-drained or sand-gravel soils classed Group I in Table R401.4.1(2).

The remaining 3 steps, the worked example and the quiz are in the course. This is a preview. The full lesson, with the step-by-step explanations, a worked example and a quick-check quiz, is inside the classroom.

More lessons for this trade

Browse all lesson previews

Ready to practice for real?

Try the real classroom free, no sign-up, or get the full course for your trade.

Independent exam preparation. Contractors Classroom is not affiliated with the Contractors State License Board, and no course can guarantee a passing result.