Electrical (C-10) · Lesson 2 of 6

Temporary Power: GFCIs and the Assured Grounding Program

"Temporary Power: GFCIs and the Assured Grounding Program" is lesson 2 of 6 in the Electrical (C-10) Learning Hub. It opens with "When temporary wiring is allowed" and works through 5 short steps, then a worked example you can check yourself against.

One-time purchase, no subscription. Law & Business included.

Steps in this lesson

  1. When temporary wiring is allowed
  2. Feeders and branch circuits
  3. Temporary poles
  4. GFCI or assured grounding: the choice
  5. Running the AEGCP

The worked example in the course applies this lesson to a realistic job in 6 steps, from "Apply it to" through "Handle the incident".

What you'll be able to do

  • Explain the main idea of "Temporary Power: GFCIs and the Assured Grounding Program" in plain language you can use on the exam.
  • Apply this step with confidence: "Temporary poles".
  • Apply this step with confidence: "GFCI or assured grounding: the choice".
  • Apply this step with confidence: "Running the AEGCP".
  • Test yourself on the worked example and the quick-check quiz inside the classroom.
Temporary Power on a Construction SiteWHICH OUTLETS NEED A GFCI?Temp pole: six 120 V, 20 A receptaclesGFCI REQUIRED (or AEGCP)5 kW generator, 2-wire, insulated circuitEXEMPT from GFCI rule240 V, 30 A welder receptacleNot 120 V: outside 2405.4(c)Kitchen receptacle in finished wiringPermanent wiring: outside 2405.4(c)TEST CLOCK (all tested Feb 1)Feb 1May 1Aug 1Cord sets: 3 monthsFixed, not exposed:6 monthsMar 15: truck runs over a cord(retest BEFORE reuse)AEGCP ALSO REQUIRESWritten program kept on the job siteA qualified person runs the programVisual check before each day's useTest continuity + correct terminal; mark dateUse GFCIs, an assured grounding program, or both - and retest after damage.Source: 8 CCR §2405.1 through §2405.4 (Low-Voltage Electrical Safety Orders)CC
The diagram for this lesson, exactly as it appears in the Learning Hub.

The first steps of this lesson

Step 1: When temporary wiring is allowed

8 CCR §2405.1 permits temporary power and lighting of 600 volts or less during construction, remodeling, maintenance, repairs or demolition; for not more than 90 days at non-permanent locations such as carnivals, music festivals, Christmas decorative lighting and Christmas tree lots; and for experimental work and emergencies. It must be removed immediately when the project or purpose ends, and temporary installations over 600 volts follow the High-Voltage Electrical Safety Orders. The 2025 California Fire Code §603.8 likewise limits temporary wiring to 90 days, with an exception for periods of construction, remodeling, repair or demolition.

Step 2: Feeders and branch circuits

Per §2405.2, feeders originate in an approved distribution center and are run as multi-conductor cord or cable assemblies; branch circuits originate in an approved power outlet or panelboard. Open conductors must be fastened at ceiling height every 10 feet, and no branch-circuit conductor may be laid on the floor. Receptacles are the grounding type, each branch circuit carries a separate equipment grounding conductor unless it is in continuous grounded metallic raceway or metallic-covered cable, no bare conductors or earth returns are allowed, and switches or plug connectors must disconnect all ungrounded conductors of each temporary circuit. Multi-conductor cords must be hard service type, and cords must be protected at doorways and pinch points.

The remaining 3 steps, the worked example and the quiz are in the course. This is a preview. The full lesson, with the step-by-step explanations, a worked example and a quick-check quiz, is inside the classroom.

More lessons for this trade

Browse all lesson previews

Ready to practice for real?

Try the real classroom free, no sign-up, or get the full course for your trade.

Independent exam preparation. Contractors Classroom is not affiliated with the Contractors State License Board, and no course can guarantee a passing result.