Steps in this lesson
Designed in Compacted Yards, Bought by the Ton
Volume First, Then Weight
Lift Thickness Rule (Caltrans Section 26-1.03D)
Compaction and Grade Tolerance (Section 26-1.03E)
Over-Building Is Expensive
The worked example in the course applies this lesson to a realistic job in 6 steps, from "Convert thickness to feet" through "Cubic yards".
What you'll be able to do
Explain the main idea of "Aggregate Base: Tons to Order, Lifts, and Grade Tolerance" in plain language you can use on the exam.
Apply this step with confidence: "Lift Thickness Rule (Caltrans Section 26-1.03D)".
Apply this step with confidence: "Compaction and Grade Tolerance (Section 26-1.03E)".
Apply this step with confidence: "Over-Building Is Expensive".
Test yourself on the worked example and the quick-check quiz inside the classroom.
The diagram for this lesson, exactly as it appears in the Learning Hub.
The first steps of this lesson
Step 1: Designed in Compacted Yards, Bought by the Ton
The plans give the aggregate base (AB) as a thickness - for example 8 inches of Class 2 aggregate base - measured after compaction. The quarry sells by the ton and each truck leaves with a weight ticket. Your job is to convert a compacted volume into tons, using a tons-per-cubic-yard figure for the material. This lesson uses 2.1 tons per compacted cubic yard as a labeled example value; the CSLB C-12 study guide's own sample question hands you a figure in the problem (1.5 tons per cubic yard), and on a job the supplier's weight tickets rule.
Step 2: Volume First, Then Weight
Compacted cubic yards = area (sq ft) x thickness (ft) / 27. Convert inches to feet before multiplying: 8 inches is 8 / 12 = 0.667 ft. Then tons = cubic yards x tons per cubic yard. Round the order up to whole truckloads, because the last partial load still costs a delivery. If AB is paid by weight on a Caltrans job, the Engineer deducts the weight of water in excess of the optimum moisture content plus 1 percent (2025 Caltrans Standard Specifications section 26-1.04), so very wet loads do not pay by the ton.