The first steps of this lesson
Step 1: Airflow Is Verified by Test
The 2025 California Energy Code, Section 150.0(m)13, applies to dwelling space-conditioning systems that use forced-air ducts to supply cooling. The installer must demonstrate both the airflow across the system and the air-handler fan efficacy by field verification and diagnostic testing. The test procedure is in Reference Residential Appendix RA3.3, which the Energy Code cites; this lesson uses the numbers the Energy Code itself prints.
Step 2: The Airflow Minimums
A single-zone central forced-air system must demonstrate, in every control mode, airflow of at least 350 CFM per ton of nominal cooling capacity through the return grilles (Section 150.0(m)13B). A zonally controlled system must deliver at least 350 CFM per ton in every zonal control mode (13C). A small duct high velocity system needs at least 250 CFM per ton (13D). Nominal capacity is the rated size, so a 4-ton system needs 4 x 350 = 1,400 CFM.
The remaining 3 steps, the worked example and the quiz are in the course. This is a preview. The full lesson, with the step-by-step explanations, a worked example and a quick-check quiz, is inside the classroom.
Independent exam preparation. Contractors Classroom is not affiliated with the Contractors State License Board, and no course can guarantee a passing result.