The first steps of this lesson
Step 1: The Pressure Test Rule
2025 CMC §1205.2 requires hydronic system piping and components to be tested at not less than one and one-half times the operating pressure, but not less than 100 psi. The test may use water or air, except that plastic pipe may not be tested with air, and the pressure must be held for not less than 30 minutes with no perceptible drop. The tests are made in the presence of the Authority Having Jurisdiction. Two exceptions: PEX, PP-R, PP-RCT, PEX-AL-PEX, PE-RT and PE-AL-PE piping may be air tested where the manufacturer's instructions authorize it and no other law prohibits it, and copper tubing shall be tested at not less than 80 psi.
Step 2: Apply the Larger-Of Rule
Compute 1.5 times the operating pressure and compare it with the 100 psi floor; the larger number is the minimum test pressure. A 60 psi loop gives 1.5 x 60 = 90 psi, so the 100 psi floor governs; an 85 psi loop gives 127.5 psi, so the multiplier governs. Flush the heating and cooling sources, piping and tubing after installation with water or a cleaning solution (§1205.3), and give the owner operating and maintenance information (§1205.1).
The remaining 3 steps, the worked example and the quiz are in the course. This is a preview. The full lesson, with the step-by-step explanations, a worked example and a quick-check quiz, is inside the classroom.
Independent exam preparation. Contractors Classroom is not affiliated with the Contractors State License Board, and no course can guarantee a passing result.