Welding (C-60) · Lesson 6 of 6Arc Welding Circuit: Return Cable Capacity, Splices, and Shutdown
"Arc Welding Circuit: Return Cable Capacity, Splices, and Shutdown" is lesson 6 of 6 in the Welding (C-60) Learning Hub. It opens with "Holders and Cables Must Match the Current" and works through 5 short steps, then a worked example you can check yourself against.
One-time purchase, no subscription. Law & Business included.
The first steps of this lesson
Step 1: Holders and Cables Must Match the Current
Only manual electrode holders intended for arc welding and cutting, and capable of handling the maximum current required, may be used; the current-carrying parts the user grips and the outer jaw surfaces must be insulated against the maximum voltage to ground (8 CCR Section 4851(d)). Welding cables must be insulated, flexible, and capable of handling the maximum current required, taking into account the duty cycle (Section 4851(e)(1)). Arc welding equipment with a functional defect shall not be used (Section 4851(j)).
Step 2: The 10-Foot Rule and Damaged Cable
Only cable free from repair or splice for 10 feet from the electrode holder shall be used, unless insulated connectors or splices with insulating quality equal to that of the cable are provided (Section 4851(e)(2)). Connectors and splices between cable lengths must be insulated connectors of equivalent capacity, and cable lugs used as connectors must make good contact with exposed metal parts insulated (Section 4851(e)(4)). When a cable wears and exposes bare conductors, that portion shall not be used until protected by insulation of equivalent performance (Section 4851(e)(3)); the California Fire Code adds that damaged cable shall be removed from service until properly repaired or replaced (Section 3506.5).
The remaining 3 steps, the worked example and the quiz are in the course. This is a preview. The full lesson, with the step-by-step explanations, a worked example and a quick-check quiz, is inside the classroom.
Independent exam preparation. Contractors Classroom is not affiliated with the Contractors State License Board, and no course can guarantee a passing result.