Out-of-Service Tanks: The 90-Day, One-Year and 365-Day Clocks
"Out-of-Service Tanks: The 90-Day, One-Year and 365-Day Clocks" is lesson 5 of 6 in the Hazardous Substance Removal (HAZ) Learning Hub. It opens with "Two Rulebooks Run at Once" and works through 6 short steps, then a worked example you can check yourself against.
One-time purchase, no subscription. Law & Business included.
Steps in this lesson
Two Rulebooks Run at Once
The CFC 90-Day Safeguard
The CFC One-Year Rule and Abandonment in Place
23 CCR Temporary Closure: 12 Months, Maybe 24
23 CCR Permanent Closure Deadlines
The Removal Checklist (CFC 5704.2.14.1)
The worked example in the course applies this lesson to a realistic job in 5 steps, starting with "CFC one-year mark".
What you'll be able to do
Explain the main idea of "Out-of-Service Tanks: The 90-Day, One-Year and 365-Day Clocks" in plain language you can use on the exam.
Apply this step with confidence: "The CFC One-Year Rule and Abandonment in Place".
Apply this step with confidence: "23 CCR Temporary Closure: 12 Months, Maybe 24".
Apply this step with confidence: "23 CCR Permanent Closure Deadlines".
Apply this step with confidence: "The Removal Checklist (CFC 5704.2.14.1)".
Test yourself on the worked example and the quick-check quiz inside the classroom.
The diagram for this lesson, exactly as it appears in the Learning Hub.
The first steps of this lesson
Step 1: Two Rulebooks Run at Once
A tank taken out of service answers to the fire code and to the state tank regulations. 2025 CFC §5704.2.13 says tanks taken out of service shall be removed under §5704.2.14 or safeguarded under §§5704.2.13.1 through 5704.2.13.2.3 and API 1604. 23 CCR Chapter 16 Article 8 (§2680 temporary closure, §2681 permanent closure) is administered by the Unified Program Agency (UPA). A HAZ contractor has to keep both clocks in view, because the shorter one controls when work must be finished.
Step 2: The CFC 90-Day Safeguard
Under 2025 CFC §5704.2.13.1.2, an underground tank not used for 90 days must either be removed per §5704.2.14 or be safeguarded: (1) flammable or combustible liquids removed from the tank; (2) all piping, including fill line, gauge opening, vapor return and pump connection, capped or plugged and secured from tampering; (3) vent lines left open and maintained. While a tank is only temporarily out of service, §5704.2.13.1.1 requires the fill line, gauge opening, vapor return and pump connection to be secure against tampering with vent lines remaining open.
The remaining 4 steps, the worked example and the quiz are in the course. This is a preview. The full lesson, with the step-by-step explanations, a worked example and a quick-check quiz, is inside the classroom.
Independent exam preparation. Contractors Classroom is not affiliated with the Contractors State License Board, and no course can guarantee a passing result.