The first steps of this lesson
Step 1: When and How Much Gets Tested
The 2025 Caltrans Standard Specifications, section 61-2.01D(3), require each pipe system to be cleaned and tested with the exfiltration, infiltration, low-pressure air, or negative air pressure method, and the field leakage test is run after backfilling. Infiltration needs the Engineer's approval if the groundwater table is low, and you use only one test method on a contiguous pipe system. Pipe systems under 1,500 feet have every joint tested; longer systems are tested at a rate of 50 joints per 100 for runs under 1 mile, 30 per 100 for 1 to 3 miles, and 20 per 100 above 3 miles. The Engineer does not accept an installation that fails, and you must stop all obvious leaks even if the total is below the allowable quantity.
Step 2: The Exfiltration Limit and Its Head Rules
For an exfiltration (water) test, section 61-2.01D(3)(b) limits leakage to 1,000 gallons per inch of nominal pipe diameter per mile of pipe per day. The minimum test pressure is 6 feet of water column above the pipe crown at the upper end (or above the active groundwater table, whichever is higher). Limit the length you test so the pressure on the invert of the lower end does not exceed 20 feet of water column. The allowable leakage goes up 8 percent for each 1.5 feet of pressure above the basic 6 feet. The test must run at least 1 hour. If you fill the pipe to let it absorb water, start the test within 72 hours after filling and finish within 24 hours after that; plastic and metal pipe need no absorption period.
The remaining 3 steps, the worked example and the quiz are in the course. This is a preview. The full lesson, with the step-by-step explanations, a worked example and a quick-check quiz, is inside the classroom.
Independent exam preparation. Contractors Classroom is not affiliated with the Contractors State License Board, and no course can guarantee a passing result.