The first steps of this lesson
Step 1: Why the Roof Must Be Checked Before You Mount
2025 California Residential Code R329.4.1 says rooftop PV systems shall be designed to structurally support the system and withstand the applicable gravity loads, and the roof they sit on must be designed and constructed to support the loads imposed by the PV system. Panels, racking and ballast add dead load, and snow can drift against them. Checking the load before you attach anything is the contractor's way of avoiding an overloaded rafter.
Step 2: Two Load Cases Where the Array Covers the Roof
R329.4.1.1 says roof areas NOT covered by PV are designed for dead loads and roof loads under R301.4 and R301.6. Roof areas that ARE covered by PV are designed for two cases. Case 1: dead load INCLUDING the PV weight, plus snow load from Table R301.2. Case 2: dead load EXCLUDING the PV weight, plus the roof live load or the snow load, whichever is greater, per R301.6. R301.4 says to use the actual weights of materials and equipment for dead load.
The remaining 3 steps, the worked example and the quiz are in the course. This is a preview. The full lesson, with the step-by-step explanations, a worked example and a quick-check quiz, is inside the classroom.
Independent exam preparation. Contractors Classroom is not affiliated with the Contractors State License Board, and no course can guarantee a passing result.